Works Included-
The supply and installation of 500m2 of plywood prior to tiling, the supply and installation of flexible
membranes to floors 1-7 prior to tiling. 100m2 porcelain tiles supplied and installed to floors 1-5, 300m2
creme luna marble installed to floors 6 and 7. Manufacture and install 100m2 creme luna wall cladding to 6th . Supply
and install 100m2 composite stone tiling to new shower rooms in basement area, porcelain mosaic to shower room floors.
Works completed in 6weeks