30 Aylesbury Street (Pinsent Mason)

Duration-5-6Weeks
Screeding-1week
Installing tiles to floors-2weeks
Regrinding of floors-2weeks
 

Phase 1- Jmgt were contracted to screed 60m2 of floors with a 60mm thick screed.
Phase 2-Supply and install 110m2 of 600x600 composite stone tiles to new reception area and to match existing main floor.
Phase3- To cut and regrout all joints in existing floors (Nightwork shifts involved)
Phase 4- Regrind and repolish 300m2 of newly tiled floors and existing floors.
Phase 5- Repolish entrance steps and throughly clean area.
 

After Jmgt completed pahse
dsc00049.jpg

Before JMGT started works
dsc00037.jpg

Finished works
dsc00046.jpg

During Works
dsc00038.jpg

Composite stone tiles after repolish and sealing
dsc00043.jpg

New reception floor matching up with old
dsc00039.jpg

Seating and lift areas
photo-0013.jpg

Main Floor
photo-0015.jpg

Seating area
photo-0011.jpg